# Self-Qualification Packet — Submission Procedure

> Step-wise administrative procedure for a BESS partner to assemble and submit a self-qualification packet to NVIDIA.

Step-wise administrative procedure for a BESS partner to assemble and submit a self-qualification packet to NVIDIA. This procedure defines the qualification pathways, ordered packet artifact structure, and per-test evidence map covering all twelve qualification tests.

**Companion to:** BESS Self-Qualification Guidelines\
**Audience:** BESS Partners and NVIDIA Reviewers\
**Correspondence:** Single channel—Partner and NVIDIA

## Governing Principle—Single Channel of Correspondence

The BESS Partner (OEM) **owns compliance** and is NVIDIA's sole point of contact.
Regardless of who executes the tests, **all correspondence, submissions, and clarifications flow only between the BESS Partner and NVIDIA**. Test labs and third-party experts are subcontracted to the partner and never correspond with NVIDIA directly.

*Figure 1   Correspondence Model*

```mermaid
flowchart LR
    nvidia["<b>NVIDIA</b><br />Reviewer"]
    partner["<b>BESS Partner</b><br />OEM - owns compliance"]
    lab["<b>Lab/Experts</b><br />Path B/C"]

    nvidia <--> |Single Channel| partner
    partner <--> |Subcontract| lab
    style partner stroke:#76b900,stroke-width:3px
```

#### Single Channel Rule

No lab-to-NVIDIA correspondence is permitted. Testing and expertise are subcontracted to the BESS Partner.

* **NVIDIA Reviewer**: Corresponds only with the BESS Partner.
* **BESS Partner (OEM)**: Owns compliance and subcontracts labs/experts as needed.
* **Lab/Experts**: Work for the partner only; no direct lab-to-NVIDIA correspondence.

## Qualification Pathways

The partner may choose one pathway for all tests, or mix pathways by test.

*Figure 2   Pathway Selection*

```mermaid
flowchart TB
    select["<b>BESS Partner selects pathway</b>"]

    pathA["<b>Path A</b>"]
    pathB["<b>Path B</b>"]
    pathC["<b>Path C</b>"]

    aDetail["<b>Self-Perform</b><br />In-house or the partner's own accredited lab."]
    bDetail["<b>3rd-Party Lab</b><br />NVIDIA-approved lab<br />Example: NLR Flatirons Campus"]
    cDetail["<b>3rd-Party Expert</b><br />Experts engaged directly<br />Example: EPRI"]

    submit["<b>Partner assembles ONE packet and submits to NVIDIA<br />(NVOnline)</b>"]
    style submit stroke:#76b900,stroke-width:3px

    select --> pathA
    select --> pathB
    select --> pathC

    pathA --> aDetail
    pathB --> bDetail
    pathC --> cDetail

    aDetail --> submit
    bDetail --> submit
    cDetail --> submit

    style pathA color:#76b900
    style pathB color:#76b900
    style pathC color:#76b900
```

#### Mixed Pathways Permitted

A partner may mix pathways per test (for example, self-perform Tests 1 to 3, run EMT validation by EPRI, and perform ride-through at Flat Iron). Any third-party work must include signed attestation in Artifact 10.

## Step-Wise Administrative Procedure

The following timeline defines the end-to-end administrative workflow, from partner intake through NVIDIA disposition.

**Process Timeline**

| Step | Owner                  | Action                                                                                                                                       | Output                                                                                                                                    |
| ---- | ---------------------- | -------------------------------------------------------------------------------------------------------------------------------------------- | ----------------------------------------------------------------------------------------------------------------------------------------- |
| 0    | Partner                | **Register & Intake:** Register intent, execute NDA, open NVOnline record                                                                    | Submission record ID                                                                                                                      |
| 1    | Partner                | **PRD Response:** Respond line by line to PRD Table 2 (Core Requirements): Comply / Deviate / Exception                                      | PRD response matrix                                                                                                                       |
| 2    | Partner                | **Disclosures:** Complete materials, safety, and compliance disclosures                                                                      | Disclosure set                                                                                                                            |
| 3    | Partner                | **Select Pathway(s):** Select pathway A/B/C per test; contract lab/experts if used                                                           | Test plan and scope attestation                                                                                                           |
| 4    | Partner / Lab / Expert | **Execute 12 Tests:** Execute all twelve qualification tests (hardware, HIL, and model-only as specified)                                    | Raw data and plots per [Appendix A](/dsx/facilities-infra/bess/appendix/a-d-submission-standards#appendix-a-data-submission-requirements) |
| 5    | Partner                | **Assemble Packet:** Assemble packet in required 00-10 artifact order                                                                        | Complete self-qualification packet                                                                                                        |
| 6    | Partner                | **Submit:** Submit package via NVOnline ([Appendix E](/dsx/facilities-infra/bess/appendix/e-dce-bess-equipment-qualification-process) steps) | Submitted packet and notification                                                                                                         |
| 7    | Partner and NVIDIA     | **Review & Clarification:** Resolve review comments through single channel                                                                   | Resolved review log                                                                                                                       |
| 8    | NVIDIA                 | **Disposition:** Issue disposition: Qualified / Conditional / Gaps                                                                           | Qualified products may be listed on Marketplace (best effort)                                                                             |

## Prescribed Packet Artifact Order

Submit as a single indexed package (folders or a bookmarked PDF) using *exactly* this numbering. Each folder maps to a section of the guidelines so reviewers can navigate directly to governing requirements.

| Order  | Artifact                                     | Contents / Source                                                                                                                                                                                                        |
| ------ | -------------------------------------------- | ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ |
| **00** | Cover sheet and submission letter            | Partner, product/model, firmware version, submission ID, pathway(s), single POC                                                                                                                                          |
| **01** | Core Requirements Checklist                  | [Appendix B](/dsx/facilities-infra/bess/appendix/a-d-submission-standards#appendix-b-core-requirements-checklist) mapping: Core Requirement -> Test IDs -> Evidence reference (reviewer's index)                         |
| **02** | PRD Response Matrix                          | Product Requirements Doc—line-by-line response to PRD Table 2 Core Requirements: Comply / Deviate / Exception                                                                                                            |
| **03** | Materials, Safety and Compliance Disclosures | Disclosure tables from Step 2                                                                                                                                                                                            |
| **04** | Standards and Regulatory Certificates        | [Appendix D](/dsx/facilities-infra/bess/appendix/a-d-submission-standards#appendix-d-industrial-standards-and-regulatory-certificates): IEEE 1547/2800, UL 9540/9540A, NFPA 855, CE/UKCA, IEC 62443, etc.                |
| **05** | Test Reports 1-12                            | One subfolder per test (05-01 to 05-12), each containing [Appendix A](/dsx/facilities-infra/bess/appendix/a-d-submission-standards#appendix-a-data-submission-requirements) evidence set                                 |
| **06** | EMT / Model Package                          | [Appendix C](/dsx/facilities-infra/bess/appendix/a-d-submission-standards#appendix-c-partner-model-package-requirements): EMT model, dq impedance plots, Nyquist/passivity artifact, version-controlled parameter export |
| **07** | Business and Supply Chain Readiness          | Section 4: throughput, 10×/24-month scale plan, supply-chain risk, failure-mode acknowledgment                                                                                                                           |
| **08** | Quality and Reliability                      | Section 5: QMS/traceability, reliability targets & model, environmental/durability, FAT/burn-in, serviceability                                                                                                          |
| **09** | Deviations and Known-Issues Log              | Consolidated list across all tests ([Appendix A](/dsx/facilities-infra/bess/appendix/a-d-submission-standards#appendix-a-data-submission-requirements) requirement)                                                      |
| **10** | Third-Party Attestation                      | Signed statement from Lab/Expert (Path B/C): scope, methods, independence. N/A for Path A                                                                                                                                |

### Required Contents for Each Test Report (Folder 05-XX)

This report must be presented in the following order.

1. Test configuration (single-line + controller settings + SOC)
2. Raw time-series data (CSV)
3. Summary plots (PDF)
4. Pass/Fail statement tied to criteria
5. Known issues and deviations ([Appendix A](/dsx/facilities-infra/bess/appendix/a-d-submission-standards#appendix-a-data-submission-requirements))

## Test Coverage and Location Map

| Test | Title                                                      | Type                                                                                                                                  | Report Folder |
| ---- | ---------------------------------------------------------- | ------------------------------------------------------------------------------------------------------------------------------------- | ------------- |
| 1    | Telemetry Verification and Data Integrity                  | Hardware (grid-connected)                                                                                                             | 05-01         |
| 2    | Grid-Adaptive V/f Regulation (Islanded)                    | Hardware (islanded bus)                                                                                                               | 05-02         |
| 3    | Current-Limit Characterization (P-first / Q-first / Mixed) | Hardware                                                                                                                              | 05-03         |
| 4    | AI Load Buffering / Ramp-Rate Smoothing                    | Hardware                                                                                                                              | 05-04         |
| 5    | EMT Validation (weak grid, SCR sweep)                      | Model-only ([Appendix C](/dsx/facilities-infra/bess/appendix/a-d-submission-standards#appendix-c-partner-model-package-requirements)) | 05-05 + 06    |
| 6    | Demand Response (DR) Dispatch                              | Hardware                                                                                                                              | 05-06         |
| 7    | LVRT / HVRT Ride-Through                                   | Hardware                                                                                                                              | 05-07         |
| 8    | Grid to Island Transition                                  | Hardware                                                                                                                              | 05-08         |
| 9    | Generator Following                                        | Hardware                                                                                                                              | 05-09         |
| 10   | Black Start                                                | Hardware                                                                                                                              | 05-10         |
| 11   | SOC Drift / Energy Balance                                 | Hardware                                                                                                                              | 05-11         |
| 12   | Control Transparency                                       | Hardware + Model                                                                                                                      | 05-12 + 06    |

#### Instrumentation Requirements

Instrumentation minimums (accuracy, sampling rate, and pre/post-trigger windows) from
[Step 4](/dsx/facilities-infra/bess/bess-qualification-overview#step-4-qualification-tests) of the BESS Qualification Overview section apply to all tests and must be evidenced in each report configuration section (05-XX, item 1).