SN2700 DC 1U Ethernet Switch Systems Quick Installation Guide

Pay Attention!
At least two people are required to safely mount the system in the
All servers and systems in the rack should be planned with the airflow All FRU components must have the same air flow direction. A mismatch in the air flow will affect the heat dissipation.
The part of the system to which you choose to attach the rails will determine the system’s adjustable side. The system’s part to which the brackets are attached will be adjacent to the
The FRU side is extractable. Mounting the rack brackets inverted to the FRU side will allow you to slide the FRUs, in and
The DC power cable should be no longer than 2m.
Package Contents
1 x System
Rail Kit for short depth (17”-24” / 432-610mm) or standard depth (24”- 34” / 610-863mm) racks
2 x DC adapter
1 x Harness RS232 2M cable – DB9 to RJ-451
The following items are not included in the package, and can be purchased separately:
Rack installation kit for SN2100 series short depth 1U switches, allows installation of one switch into standard depth racks (23.6"-31.5" / 600- 800mm).
Quantity |
Item |
X4 |
![]()
|
X8 (of each) |
![]()
|
X2 (of each) |
![]() |
X2 |
![]()
|
X1 |
![]()
|
If anything is damaged or missing, contact your NVIDIA representative at Networking-support@nvidia.com.