The following instructions describe how to install the OCP 21” adapter tray, and how to mount the SN5600D switch system in the adapter tray.

Rack Preparation:

  • Ensure the OCP rack is properly leveled and secured to the floor according to the site's standards.

  • The rack must be equipped with L-shaped support brackets at the target installation height.

Warning

Heavy Equipment: Always use a server lift or two people when handling the switch and the adapter tray.


Required Components:

2 x L‑shaped support brackets (left and right)

image-2026-1-14_12-5-45-1-version-1-modificationdate-1769087000510-api-v2.png

1 x Adapter tray

image-2026-1-14_12-7-7-1-version-1-modificationdate-1769086999267-api-v2.png

1 x SN5600D Switch Rail-kit

image-2026-1-14_12-6-13-1-version-1-modificationdate-1769086999713-api-v2.png

1 x SN5600D Switch system

image-2026-1-14_12-6-4-1-version-1-modificationdate-1769087000083-api-v2.png

Step 1: Installing the L-Shaped Brackets into the OCP Rack

    1. Define the height: Select the desired OU height within the 21" OCP rack.

    2. Mount the Brackets: Align the brackets with the rack's pre-punched holes.

    3. Engagement: Angle the rail in to seat the hooks into the corresponding locations. Make sure that the latch side of the brackets faces the rear of the rack.

    4. Verification: Confirm that the latches are fully engaged and there is no interference with other rack parts.

image-2026-1-15_11-37-55-1-version-1-modificationdate-1769086991710-api-v2.png

Step 2: Install the Rail-Kit onto the Adapter Tray

    1. Install the standard 19" Rail-Kit onto the adapter tray's front and rear EIA posts.

      image-2026-1-14_12-11-57-version-1-modificationdate-1769086997930-api-v2.png

    2. Follow assembly steps 1-3, as detailed in the SN5600D Rail-Kit Section:

      image-2025-3-16_16-51-41-version-1-modificationdate-1769086993400-api-v2.png

      image-2025-3-16_16-34-9-version-1-modificationdate-1769086993030-api-v2.png

Step 3: Mount the Adapter Tray into the OCP Rack

    1. Select the RU position

      • Choose the 2U window (e.g, RU 20-21) where the switch system will be located, and confirm that the L‑shape support brackets (or shelf rails) are installed at that height.

    2. Placement: Rest the bottom flanges of the adapter tray onto the two L-shaped support brackets previously installed in the rack.

    3. Securing: Slide the tray along the brackets until it latches securely into position.

  1. image-2026-1-15_11-37-11-1-version-1-modificationdate-1769086992187-api-v2.png

    1. Final Checks:

      • Ensure that the tray is correctly seated and does not obstruct doors or busbars.

      • Verify the tray's rear extenders are properly inserted into the rear flanges of the L-shaped brackets on both sides.

        image-2026-1-14_12-44-49-1-version-1-modificationdate-1769086994713-api-v2.png

      • Confirm that the front hooks of the adapter tray are latched to the rack's front posts.

        image-2026-1-14_14-15-34-1-version-1-modificationdate-1769086994170-api-v2.png

Step 4: Assemble the Switch Rail-Kit

Follow assembly step 4, as detailed in the SN5600D Rail-Kit Section:

image-2025-3-16_16-35-14-version-1-modificationdate-1769086992630-api-v2.png

Make sure to secure the chassis in the rack by tightening the designated screws.

image-2026-1-14_14-24-36-version-1-modificationdate-1769086993783-api-v2.png

Step 5: Install the Switch System in the Adapter Tray

    1. Using the pre-installed rail-kit, slide the switch system into the adapter tray until it is fully engaged.

    2. Secure the chassis by tightening the designated screws.

    3. Perform a final inspection of both the front and rear of the rack to ensure the system is properly seated and the busbar connection is fully plugged.