SN5600D OCP 21" Adapter Tray Installation Instructions
The following instructions describe how to install the OCP 21” adapter tray, and how to mount the SN5600D switch system in the adapter tray.
Rack Preparation:
Ensure the OCP rack is properly leveled and secured to the floor according to the site's standards.
The rack must be equipped with L-shaped support brackets at the target installation height.
Heavy Equipment: Always use a server lift or two people when handling the switch and the adapter tray.
Required Components:
2 x L‑shaped support brackets (left and right) |
|
1 x Adapter tray |
|
1 x SN5600D Switch Rail-kit |
|
1 x SN5600D Switch system |
|
Step 1: Installing the L-Shaped Brackets into the OCP Rack
Define the height: Select the desired OU height within the 21" OCP rack.
Mount the Brackets: Align the brackets with the rack's pre-punched holes.
Engagement: Angle the rail in to seat the hooks into the corresponding locations. Make sure that the latch side of the brackets faces the rear of the rack.
Verification: Confirm that the latches are fully engaged and there is no interference with other rack parts.
Step 2: Install the Rail-Kit onto the Adapter Tray
Install the standard 19" Rail-Kit onto the adapter tray's front and rear EIA posts.
Follow assembly steps 1-3, as detailed in the SN5600D Rail-Kit Section:
Step 3: Mount the Adapter Tray into the OCP Rack
Select the RU position
Choose the 2U window (e.g, RU 20-21) where the switch system will be located, and confirm that the L‑shape support brackets (or shelf rails) are installed at that height.
Placement: Rest the bottom flanges of the adapter tray onto the two L-shaped support brackets previously installed in the rack.
Securing: Slide the tray along the brackets until it latches securely into position.
Final Checks:
Ensure that the tray is correctly seated and does not obstruct doors or busbars.
Verify the tray's rear extenders are properly inserted into the rear flanges of the L-shaped brackets on both sides.
Confirm that the front hooks of the adapter tray are latched to the rack's front posts.
Step 4: Assemble the Switch Rail-Kit
Follow assembly step 4, as detailed in the SN5600D Rail-Kit Section:
Make sure to secure the chassis in the rack by tightening the designated screws.
Step 5: Install the Switch System in the Adapter Tray
Using the pre-installed rail-kit, slide the switch system into the adapter tray until it is fully engaged.
Secure the chassis by tightening the designated screws.
Perform a final inspection of both the front and rear of the rack to ensure the system is properly seated and the busbar connection is fully plugged.