Plan Your Deployment#
Complete the NVIDIA Mission Control Deployment Planning Checklist before the installation begins. The workbook helps the customer and deployment team collect software installation inputs, confirm that required artifacts are available, and identify missing information that can delay the installation.
Download the NVIDIA Mission Control Deployment Planning Checklist.
The Software Installation worksheet tracks inputs and artifacts for Kubernetes, NetQ, Autonomous Hardware Recovery (AHR), Autonomous Job Recovery (AJR), Power Reservation Steering (PRS), NVIDIA Run:ai, and NMC Launchpad.
The customer project lead should coordinate completion of the workbook with the platform administration, security, and installation teams. Complete each applicable row, assign its status, and select Not Applicable when an item does not apply to the deployment.
Warning
Do not enter passwords, private keys, product keys, access tokens, or other secrets in the workbook. Record only whether each secret is available and where the installation team can retrieve it from an approved secrets store.
Review the completed workbook with the installation team before work begins. The workbook supports deployment planning but does not replace the product requirements. Confirm each requirement against NVIDIA Mission Control Prerequisites and then review Installation Overview before choosing an installation path.