This document is the canonical public release policy for NVIDIA Infra Controller (NICo). It describes how NICo is branched, versioned, released, supported, and evolves its public compatibility guarantees.
TL;DR
- Use the latest final
vX.Y.Ztag for production-style deployments. main,-pr, and-rcbuilds are for prerelease testing.- Every month,
mainbranches torelease/vX.Y; after one month of QA, that branch becomes the finalvX.Y.0release. - Patch releases stay on the same
release/vX.Ybranch and ship only when fixes warrant them. - NICo keeps three minor releases visible: Current, Maintenance, and EOL. Upgrades are supported from EOL to Maintenance or Current, from Maintenance to Current, and to newer patches within the same minor version. Anything older than EOL has no supported upgrade path.
- Guaranteed public APIs stay backward-compatible within a major version. Breaking removals require a future major release and at least one full three-month roadmap window of notice.
Branches
NICo uses just two long-lived branch types — main and per-minor-version
release branches — together with SemVer tags that distinguish prereleases,
release candidates, and final releases. The -rc and -pr suffixes are tag
suffixes, not branch suffixes.
Main Branch — Ongoing Development
All changes land on main first. There is no expectation of stability on
main; it is not QA tested. The only tests that gate changes to main are the
automated tests that run in CI. Features can be incomplete and bugs can be
present at any commit.
Use main if you want early access to in-progress features and you accept that
things will sometimes be broken.
Release Branches
When development for a minor version is feature-complete, a new long-lived
release branch (for example, release/v2.1) is cut from main. This single
branch holds the entire life of that minor version:
- During the one-month QA window, the branch carries
vX.Y.Z-rcNtags as fixes land — these are release candidates, not final releases. - After QA signs off, a final
vX.Y.0tag is cut on the same branch. - After GA, the branch continues to host patch releases (
vX.Y.1,vX.Y.2, and so on) as they are tagged.
The branch itself never carries an -rc suffix — only the tags on it do. The
latest non--rc tag on this branch is what most users should deploy. Refer to
Tag Naming below.
Tag Naming
NICo uses Semantic Versioning of the form vX.Y.Z:
X— major versionY— minor versionZ— patch version
The following tag forms appear in the repository:
-
vX.Y.0— A minor release. Published as a GitHub release fromrelease/vX.Y. -
vX.Y.Z(whereZ > 0) — A patch release on top ofvX.Y.0. Also published as a GitHub release fromrelease/vX.Y. -
vX.Y.Z-rcN(for example,v2.1.0-rc1orv2.1.5-rc3) — A release candidate. Applied to commits onrelease/vX.Yduring the QA window for whichever release is being prepared (initial.0or a later patch).All four elements — major, minor, patch, and RC number — are always present. Patch releases live on the same
release/vX.Ybranch and are distinguished only by the tag. So the first release candidate forv2.1.5is taggedv2.1.5-rc1onrelease/v2.1, and the final tag (after QA signs off) isv2.1.5. -
vX.Y.Z-pr(always withZ = 0, for example,v2.2.0-pr) — Applied tomainimmediately after a release branch is cut, to indicate thatmainis now the prerelease for the next minor version.All three numeric elements are present for consistency with
-rcNtags. For example, the dayrelease/v2.1is cut,mainis taggedv2.2.0-pr, signaling thatmainis now pre-v2.2.0.
Every published minor and patch release is available on GitHub Releases, tagged with its Semantic Versioning (SemVer) version.
Release Cadence
NICo follows a fixed monthly cadence with a one-month QA window.
We also aim to avoid releases during major US and international holiday periods — including, but not limited to, the late-December/early-January end-of-year break, US Thanksgiving week, Lunar New Year, and Diwali — out of respect for the work/life balance of contributors and operators who observe them. When the published schedule would otherwise land a release inside one of these windows, the release is rescheduled to the next practical date.
Three-Month Rolling Roadmap
NICo’s three-month rolling roadmap is published as a pinned GitHub issue in this repository. It is maintained alongside the monthly release cadence. The roadmap gives contributors, QA, and operators a current view of the next three planned minor-release cycles, including:
- planned feature themes or notable work targeted for each minor release;
- expected code-complete dates, QA windows, and final release targets;
- known schedule risks, dependency risks, or holiday-window adjustments; and
- items that have moved into or out of a cycle since the previous update.
The roadmap is refreshed at least once per month, typically after the monthly branch cut and prerelease tag, so it always rolls forward to keep three months visible. It is planning guidance rather than a release guarantee: features can move between cycles as priorities change, QA findings emerge, or release dates are adjusted.
Minor Releases (X.Y.0)
Every month:
- Code complete (last day of each month): a new release branch (for
example,
release/v2.1) is cut frommain. - Immediately after the cut,
mainis tagged withvX.(Y+1).0-prto mark the start of the next prerelease cycle onmain. - The release branch is stabilized and QA tested for one month. During this
window, release-candidate tags (for example,
v2.1.0-rc1,v2.1.0-rc2, and so on) are applied to commits on the branch as QA cycles through them. - Final minor release (last day of the following month): when QA signs off,
a
vX.Y.0tag is cut on the samerelease/vX.Ybranch and published as a GitHub release.
In short: minor releases ship one month after code complete.
Patch Releases (X.Y.Z)
Patch releases happen on the release/vX.Y branch after the corresponding
vX.Y.0 has shipped. They are cut as needed — primarily for critical bug
fixes (data loss, security, production-blocking regressions) or significant
issues that cannot wait for the next minor release. There is no fixed patch
cadence; patches ship when the fixes warrant them.
Patch releases go through their own QA window, scoped to the changes being shipped. The mechanics are the same as for a minor release but use a patch-versioned RC tag:
- Candidate commits are tagged on
release/vX.YasvX.Y.Z-rcN(for example,v2.1.5-rc1,v2.1.5-rc2). - QA executes the relevant test plans against the RC tag.
- After QA signs off, the final
vX.Y.Ztag is cut on the same branch.
Note that patch releases do not get their own branch. All v2.1.* work
lives on release/v2.1; only the tags distinguish a patch RC from the final
patch release. Each final patch release is published on
GitHub Releases with a vX.Y.Z tag.
Which Version Should I Use?
Bugs found on a tagged release (vX.Y.Z with no -rc or -pr suffix) are
treated with the highest priority and are tracked as QA test escapes —
defects that slipped past the QA window and require a follow-up fix, typically
in the next patch release.
Support Policy
At any point in time, exactly three minor releases are visible to users, each in a different support tier. The tiers shift forward by one slot each time a new minor release passes QA.
The middle tier is called Maintenance in this document. This is the more standardized industry term for “still supported, but on a higher bar for changes” (for example, Kubernetes and PostgreSQL community releases). In most ecosystems, deprecated implies “scheduled for removal,” which is closer to what we mean by EOL.
Tier Transitions
When release vX.Y passes QA and becomes Current:
- The release that was Current (
vX.(Y-1)) moves to Maintenance. - The release that was Maintenance (
vX.(Y-2)) moves to EOL and stops receiving fixes. - The newly Current release (
vX.Y) begins accepting patch releases under the normal bar.
Because the monthly cadence is fixed, each minor release spends roughly one month as Current, one month as Maintenance, and is then EOL.
Fix Backporting
NICo uses a four-level severity scheme aligned with common industry practice (refer to, for example, the Kubernetes patch-release criteria and the CVSS v3.1 severity ratings for security issues):
A change is anything that is not just a bug fix: new APIs, new fields, new flags, new dependencies, version bumps of major dependencies, refactors, performance improvements that are not fixing a regression, and so on.
The bars below apply on top of these definitions:
-
Current — “normal bar.” Accepts Critical, High, and Medium bug fixes, shipped through patch releases (
vX.Y.Z). Low-severity fixes are accepted when they are low-risk; they can also be deferred to the next minor release. New feature work does not land on Current — features land inmainand ship in the next minor release.Small, low-risk changes (for example, a one-line configuration option or a clearer error message) can occasionally land alongside fixes when their value clearly outweighs the risk of destabilizing a supported release. This is the exception, not the rule.
-
Maintenance — “higher bar.” Accepts Critical and High only. Medium- and Low-severity bug fixes are not backported, and no changes (in the sense above) are accepted.
The intent is to keep Maintenance releases as stable and predictable as possible: only fixes that would otherwise compel a user to upgrade are backported.
-
EOL receives no fixes regardless of severity. Users on EOL releases should plan an upgrade.
When in doubt about whether a fix clears the Maintenance bar, default to “no” and link the original fix PR in a comment so the decision is auditable.
Upgrade and Downgrade Support
In other words, you can skip the Maintenance tier when upgrading from EOL straight to Current, but you may not move backward to an older minor (or to an older patch within the same minor). If a Current release introduces a problem that blocks you, the supported recovery is a forward-fix in the next patch release, not a downgrade.
Downgrade support is being tracked as a potential future capability in issue 2019, Graceful Rollbacks of NICo to the previous minor version; track that issue for the latest state.
Backward Compatibility
Breaking changes are not allowed anywhere in the codebase for anything that falls under our API guarantees.
Deprecation and Breaking-Change Notice
Guaranteed public APIs can be deprecated before a future breaking change, but deprecation is a warning, not removal. A deprecated guaranteed API must remain functional for the rest of the current major version.
Removal of, or an incompatible behavior change to, a guaranteed public API is allowed only in a future major release. Any such change must be announced in the release notes and the three-month rolling roadmap, and should include a replacement or migration path when one exists.
When practical, deprecated public APIs should also produce an operator-visible warning, such as an API warning, CLI warning, log message, or release-note callout.
The minimum notice period for a breaking change to a guaranteed public API is one full three-month rolling-roadmap window before the first release that removes or changes it incompatibly. Emergency exceptions for security, data corruption, or similarly severe issues must be called out explicitly in the release notes.
This notice policy applies only to the guaranteed surfaces below. Internal APIs and storage formats listed under What Is Explicitly Not Guaranteed can change between releases.
What Is Guaranteed to Remain Backward Compatible
- The NICo REST API.
- The NICo CLI (
nicocli) — command names, arguments, flags, values, and exit codes. - Configuration file structures — keys, values, filenames, and locations.
- Environment variable names and values consumed by NICo components.
If you depend on any of the above, you can rely on them not changing incompatibly within and across releases.
What Is Explicitly Not Guaranteed
The following are considered internal and can change without notice between releases:
- The gRPC API and protobuf message contents.
- The admin CLI (also referred to as the debug CLI) — a lower-level tool intended for operators and developers, not end users.
- The admin UI (also referred to as the debug UI) — same audience as the admin CLI.
- The Vault data model — how secrets are laid out inside HashiCorp Vault.
- The PostgreSQL database schema used by NICo services. Refer to issue #2019 for the current state of this guarantee (tracked alongside downgrade support, which depends on it).
- Any other internal API contract between NICo services, or persistent data formats used only by NICo itself.
If you build automation that depends on any of the unguaranteed items above, expect to update it across NICo releases.
Glossary
A few terms used on this page that are not always obvious:
- Code complete — the point in the cycle at which feature work for a minor
version stops and stabilization begins. On this date, the release branch is
cut from
main. - Release candidate (rc) — a tagged build on a
release/vX.Ybranch that is a candidate for release, pending QA sign-off. Identified by the-rcNsuffix on the tag (for example,v2.1.0-rc1,v2.1.5-rc2). Note:-rcis a tag suffix only; there is norelease/...-rcbranch. - Prerelease (pr) — a build of
mainthat is on its way to becoming the next minor release. Identified by the-prsuffix on a tag (for example,v2.2.0-pr). - QA sign-off — the formal acknowledgment from QA that a release candidate has passed its test plan and can be promoted to a final release.
- QA test escape — a defect discovered in a tagged, signed-off release that was not caught during the QA window. These are treated as high-priority and typically fixed in a subsequent patch release.
- SemVer — Semantic Versioning, the
vX.Y.Zscheme used by NICo whereXis major,Yis minor, andZis patch. - Current — the most recent GA minor release. Receives bug fixes under the normal bar through patch releases.
- Maintenance — the minor release one version behind Current. Still supported, but only for fixes meeting a higher bar (regressions, security fixes, critical blockers).
- End-of-Life (EOL) — the minor release two versions behind Current. No longer receives fixes. Users should upgrade to Maintenance or Current.
- Three-month rolling roadmap — a planning view of the next three planned minor-release cycles. It is refreshed monthly and used for coordination, not as a release guarantee.